What Is a Construction Change Order?
A construction change order is a written amendment to an existing construction contract. It modifies the original scope of work, the contract sum, the substantial-completion date, or the material specifications. The industry-standard instrument is AIA G701 Change Order, executed by owner, contractor, and architect (where the agreement uses architect administration under AIA B101). On ConsensusDocs jobs the parallel form is ConsensusDocs 202. AIA A201 § 7.2 conditions extra compensation on a written change order; § 7.3 governs construction change directives used when owner and contractor cannot agree on price before the work must proceed.
Three sources generate the change-order workload on most projects. First, owner-directed scope changes (added rooms, upgraded finishes, layout reconfiguration). Second, latent or differing site conditions discovered after demolition or excavation, governed by the differing-site-conditions clause in AIA A201 § 3.7.4 and analogous federal contracting rules at FAR 52.236-2. Third, design errors or omissions for which the architect or engineer carries professional-liability coverage under AIA B101 § 8.1.1. Each category triggers distinct claim-notice obligations: A201 § 15.1.3.1 requires written notice within 21 days of the event giving rise to the claim, or the right to additional compensation is waived.
The change order also closes the parol-evidence door. Without G701 in the file, oral promises about extra work meet the no-oral-modification clause and are usually unenforceable (Restatement (Second) of Contracts § 213). Several states harden the rule for residential work: California BPC § 7159(d) requires every change to be in writing and to reset the three-day right of cancellation for any cumulative price increase; Maryland Bus. Reg. § 8-501 caps overruns at 10 percent absent a written change order; Massachusetts 780 CMR 110.R6 requires the homeowner's signature on every contract amendment.
Differing site conditions and the Spearin doctrine
When the owner furnishes plans and specifications, the Spearin doctrine (United States v. Spearin, 248 U.S. 132 (1918)) makes the owner liable for design defects. The contractor that encounters subsurface conditions materially different from those indicated in the contract documents (a Type I differing site condition) is entitled to a change order under FAR 52.236-2 on federal jobs and under AIA A201 § 3.7.4 on private work. Conditions of an unusual nature differing materially from those ordinarily encountered (a Type II) likewise support recovery. The contractor must give prompt written notice before disturbing the condition, or the claim is waived.
No-damage-for-delay clauses and time impact
Many private contracts include no-damage-for-delay clauses that limit the contractor's recovery for owner-caused delay to a time extension only, with no monetary damages. Courts enforce these clauses subject to recognized exceptions: bad faith, active interference, fundamental breach, and delay not within the parties' contemplation (Corinno Civetta Constr. v. City of New York, 67 N.Y.2d 297 (1986)). California Public Contract Code § 7102 voids no-damage-for-delay clauses on public works for delay unreasonably caused by the public agency. The change order should state the time impact in days and identify whether monetary delay damages are recoverable in addition to the time extension.
Scope Changes
Add, remove, or modify work with a clear written record.
Price Adjustment
Document cost increases, decreases, and running contract total.
Timeline Impact
Extend or adjust the completion date with documented justification.
Change Order Form Preview
Construction Change Order
Contract Amendment
Change Order #: [CO-___]
Original Contract Date: [Date] | Project: [Name]
DESCRIPTION OF CHANGE
[Detailed description]
REASON FOR CHANGE
[Owner request / Unforeseen condition / Design change]
COST IMPACT
Original Contract: $[Amount] | This CO: $[+/- Amount] | New Total: $[Amount]
TIME IMPACT
Days Added/Subtracted: [#] | New Completion Date: [Date]
Key Components of a Change Order
Each component below maps to a specific provision of AIA A201 General Conditions or its ConsensusDocs equivalent. Sequential numbering supports the contractor's records obligation under § 7.3.7. Cost breakdown supports the pricing methods enumerated in § 7.3.3. Time impact supports the schedule-extension claim under § 8.3. Owner and contractor signatures satisfy the no-oral-modification bar in § 7.2 and the parol-evidence rule.
Markup caps and cost-of-the-work definitions
AIA A201 § 7.3.3.3 permits cost-plus pricing on change orders where the parties cannot agree on a lump sum. The definition of cost of the work in AIA A102 § 7 controls what the contractor may charge: direct labor at agreed rates, materials at invoice cost, subcontractor billing, equipment rental at Blue Book rates, and bond and insurance premium adjustments. Markup caps are typically 10 to 15 percent on direct work and 5 percent on subcontractor work. Some state public-works statutes cap change-order markup more strictly: California Public Contract Code § 10240 et seq. for state projects.
Retainage release on completed change-order work
Change-order work is included in the schedule of values on AIA G703 and is subject to the same retainage as the base contract (typically 5 to 10 percent under § 9.3). State prompt-payment statutes set retainage caps and release deadlines: Texas Property Code § 28.003 limits private-job retainage to 10 percent and requires release within 30 days of acceptance; Florida Statutes § 715.12 imposes interest on late payments. The change order should state whether the changed work carries the same retainage rate as the base contract and when retainage releases.
| Component | Purpose | Details |
|---|---|---|
| Change Order Number | Sequential tracking | CO-001, CO-002, etc. for audit trail |
| Description of Change | Documents scope modification | Detailed description of added, removed, or modified work |
| Reason for Change | Categorizes the cause | Owner request, unforeseen condition, design revision |
| Cost Breakdown | Itemizes price impact | Labor, materials, subs, equipment, markup, running total |
| Time Impact | Adjusts the schedule | Days added/subtracted, new completion date |
| Contract Summary | Shows running totals | Original price, total COs to date, adjusted contract price |
| Supporting Documents | Provides evidence | Photos, sketches, subcontractor quotes, specifications |
| Signatures | Authorizes the change | Owner and contractor signatures with dates |
How to Issue a Change Order
The five steps below track the AIA A201 § 7.2 and § 15.1 workflow. Each step closes a class of recurring dispute: unauthorized extras, pricing disagreement, schedule impact, owner approval, and record-keeping gaps that defeat bond claims later.
Notice of claim within 21 days
AIA A201 § 15.1.3.1 requires the claiming party to give written notice of a claim within 21 days of the event giving rise to the claim or first recognition of the condition. Failure to give timely notice waives the claim under most state contract law (Triple R Paving v. Broward Cnty., 774 So. 2d 50 (Fla. 4th DCA 2000)). The notice should describe the changed condition, identify the contract provision invoked, and reserve the right to submit a claim for adjusted compensation and time. Issue the notice even when pricing data is incomplete; the detailed claim follows under § 15.1.4.
Identify and Document the Change
Describe the changed work in detail. Include photos of existing conditions, reference the affected sections of the original contract, and categorize the reason (owner request, unforeseen condition, or design change).
Price the Changed Work
Prepare a detailed cost breakdown: labor hours and rates, material quantities and costs, subcontractor quotes, equipment rental, and the contractor's overhead and profit markup. Reference the change order pricing method from the original contract.
Assess Timeline Impact
Determine whether the change affects the critical path. Calculate the number of additional or subtracted days and update the projected completion date.
Submit for Review and Approval
Present the completed change order to the owner for review. Include all supporting documentation. Allow reasonable time for review and questions.
Obtain Signatures
Both parties sign and date the change order. Distribute copies to the owner, contractor, architect (if applicable), and file. Log the change order in the project change order register.
Frequently Asked Questions
Common questions about construction change orders, pricing, approval, and documentation.
Official Resources
Authoritative resources on construction change orders and contract administration.
Create Your Change Order
Document any modification to your construction contract with a professional change order form.
Create DocumentNo account required. Free to create and preview.



